Earth BuildingProject Partner: Kunming University of Science and TechnologyProject Information:
|
|
Progress:
May 2024 - The final house was completed and passed the inspection and acceptance.
Jun - Dec 2023 - Additional 2 households joined the building programme. By Dec, 5 houses were built with acceptance and 1 household was currently undergoing renovation.
Oct 2022 - 4 more households decided to build their houses. Craftsman training was conducted and relevant foundation work commenced.
Aug 2022 - Total 7 houses were built successfully with acceptance.
Jun 2022 - 3 houses were built; 4 houses were under rammed earth construction.
Mar 2022 - 6 households (4 houses) had completed rammed earth construction work; 3 houses were under rammed earth construction.
Dec 2021 - Commencement of foundation work for 5 households.